Owner/developer: Springfield Public Schools
General contractor: Carson-Mitchell Inc.
Architects: H Design Group LLC and The Hollis & Miller Group Inc. (Kansas City)
Engineers: Olsson Inc., civil; The Hollis & Miller Group, structural; and CJD Engineering LLC, mechanical, electrical and plumbing
Size: 42,000 square feet
Estimated cost: $13.89 million
Lender: None
Estimated completion: August
Project description: The expansion at Sunshine Elementary School features four new classrooms, a storm-shelter gym, a new kitchen and front entry, said Jason Carson, CEO of general contractor Carson-Mitchell. When finished, the school will comprise 59,000 square feet and have a capacity for 350 students. Carson said renovation of 17,000 square feet includes converting the old kitchen and gym into an art room and a multipurpose space. The project is part of a $168 million bond proposal approved by voters in April 2019 for construction or renovations at 39 schools in the district.
Missouri State University’s science building, built in 1971 and formerly called Temple Hall, is being reconstructed and updated.